As part of the Knox Regional Netball Centre Masterplan, the project will deliver:
- two additional indoor courts
- new change rooms and a function room
- an observation deck
- upgrades to the existing stadium including improved accessibility and storage
- extra 180 parking bays including accessible parking spaces
- improved pedestrian walkways and landscaping
- public art installations
- 4 star energy initiatives including solar power, recycled materials, natural light and rain water retention systems.
- additional office space, first aid room and multi-purpose function room
Find out more about the Draft Masterplan
Project timing
Phase | Timing |
Concept development | June 2019 – June 2020 |
Detailed design and approval | June 2020 – May 2021 |
Procurement and tender | June 2021 – October 2021 |
Construction start | November 2021 |
Construction completion | Stage 1 - New indoor stadium February 2023 Stage 2 - Refurbishment of existing stadium - October 2023 |
Project funding
The project is being delivered in partnership with the Victorian and Australian Governments.