About the projects
Project 1: Construction of a new modular changeroom facility (Completed).
Project 2: Refurbishment of the existing sports pavilion (Current project).
Project timelines
Project | Timeframe |
---|---|
Modular changerooms | Late 2024 - Mid 2025 |
Existing pavilion refurbishment | Late 2025 - Early 2026 |
Scope of works
Modular changerooms
The new modular changerooms will include:
- Four all-inclusive changerooms with adjoining amenities.
- Accessible showers, toilets, and ambulant facilities.
- Dual first aid rooms.
- Umpires’ changerooms with adjoining amenities.
- A cleaners’ room.
- Public unisex accessible and ambulant amenities.
- An arts project integrated into the building design.
Existing pavilion refurbishment
The refurbishment will feature:
- Internal upgrades to the kitchen, amenities, and clubrooms.
- External works, including concrete footpaths.
- A covered walkway connecting the existing pavilion and the new modular changerooms.
Estimated project budgets
- Modular Changerooms Construction: $1.5 million
- Existing Pavilion Refurbishment: estimated $800,000
Construction phases
The project will be completed in the following stages:
Phase 1: Modular construction off-site
Phase 2: On-site installation of the modular facility
Phase 3: Completion of the modular facility
Phase 4: Refurbishment of the existing pavilion
Phase | Timing | Activity |
---|---|---|
Phase 1 | Late 2024 | Start of off-site modular construction |
Phase 1 | Late 2024 | Off-site modular construction completed |
Phase 2 | Mid-2025 | On-site modular installation completed |
Phase 3 | Mid-2025 | Modular facility ready for use |
Phase 4 | Mid-2025 | Pavilion refurbishment begins (TBC) |
Phase 4 | Early 2026 | Pavilion refurbishment completed (TBC) |
Location
The Park Ridge Reserve pavilion is located at 208 Dandelion Dr, Rowville VIC 3178.
Why this project is happening
The upgrade is needed because:
- The pavilion is outdated and lacks adequate facilities.
- More storage and first aid spaces are required.
- The design needs to support inclusivity and accessibility.
The project will use sustainable building practices.
Impacts
- The car park will have reduced parking availability throughout 2025 due to construction vehicles.
- The car park will be closed for a few days during modular installation (early 2025).
- The existing pavilion will remain operational until refurbishment begins in mid-2025.
- The modular will be operational while the pavilion refurbishment is underway.
- Disruption to reserve users will be kept to a minimum.
Map

Areas of Park Ridge that will be affected by upgrade works in 2025 / 2026.